Case study · client name withheld

From scattered purchase records to one operating view.

A custom manufacturing operation needed to know what each build required, what had been ordered, and what was at risk before a missing part stopped the work.

Reno solar installation illustrating one operating view across parts, purchasing, and order status
One operating view. Earlier action. Fewer surprises.

How we know

In the tracker's first week, about 90 orders turned out to have no confirmation number on file; the team found and filled them in. In the first two months of the new purchase-order path, more than 40 numbered POs went out, each tied to an approval. Both figures are rounded and come from Harry's own records.

The limit

Missing confirmations did not mean 90 failed orders. It meant nobody could tell which orders needed a call. This case claims earlier visibility, not a revenue gain.

The problem

Each build had its own copied spreadsheet, and nobody could see across them.

Every van build's parts list lived in a copy of the last build's file. Open orders across builds were invisible, stalled orders showed up on install day, and hand-typed totals did not match price times quantity. Purchase orders went out in mixed formats, invoices went straight to leadership, and nobody could say who had approved a given purchase.

Diagnose

Trace one build from parts list to receipt.

One build's requirements were connected to its purchase records and checked against the questions the shop actually asks: who ordered it, from whom, when, for which build, at what status, and with what confirmation. The gaps in those answers set the scope.

Build the tracker

Keep the spreadsheet. Give it rules.

One workbook now covers every build, and a new build is cloned from the last one. It has a status pipeline (need to order, being ordered, ordered, delivered), an automatic flag on anything ordered and not delivered after five days, a vendor-grouped order list that writes status back to each build, delivery countdowns, a change log, and restore steps. A go/hold parts report goes to the shop before each build starts.

Build the PO path

Number every purchase order and route it through one approval.

Purchase orders are generated from the inventory system as numbered, templated documents. Every vendor invoice and purchase request passes through one documented approval step, and backorders get a follow-up owner instead of a hope.

What changed, and what did not

Late parts now show up as a flag, not as an empty bay.

The shop can tell ordered, confirmed, received, late, and unresolved apart without reconstructing the story from email. The tool is still a spreadsheet. It works because the ordering process now creates the data the sheet displays, and because the people who place orders are the ones who asked for the flags.

Still open: the sync between the tracker, the cost sheets, and the inventory system is designed and not yet built. Until then, one person reconciles them weekly.

The operations consulting service behind this work

Free 30-minute call

Which order would you not be able to find today?

If the answer takes more than a minute, that is the diagnostic. Describe how purchasing works now and we will start there.